Important Campus Construction Updates

LU Riverside Trail: paving is complete! Next up – trail lights and access gates.

Kohler Hall: work continues on the window install and basement renovation.

Music Drama: the ceilings have been removed and currently the demo of the old HVAC systems is underway.

Warch Campus Center: work has begun on the 2nd floor removing of existing flooring, which will be replaced with terrazzo.

Drew St. Pedestrian Bridge: work continues as the foundational structures are installed.

As always – safety first! Do not enter construction areas! Please be mindful of your surroundings at all times as most construction and projects are in full swing. Should you have questions or see anything concerning as you’re out and about, please contact Katherine in Facility Services at: Katherine.lehman@lawrence.edu or at ext. 6893

Silent Bike Auction set for June 28

Silent Bike Auction

Located at Facility Services, 235 E. Water Street (please note: the LU Trail will be closed)

Tuesday, June 28,  8:00 a.m. – 3:00 p.m.

No bids accepted after 3:00 p.m. on Tuesday, June 28

Winners will be notified by Wednesday, June 29.

*Payment due on day of pick up (exact cash or check made out to Lawrence University)

All bikes must be picked up by Thursday, June 30 no later than 3 PM

All unclaimed bikes will be awarded to the next highest bidder

All bikes are sold “AS IS”

Important Campus Construction Updates

Groundbreaking for the construction of the new Gateway Arch will begin next week!

The LU Trail along the river is being paved next week starting Monday, June 27th, and will be inaccessible for the duration of the week.

Colman Hall is looking sharp with some fresh paint on floors 1 & 2, the North wing and lofts, and new carpeting in the hallways on floors 2, 3 and 4! Next up – new ceiling tiles on floors 2, 3 & 4.

Work to replace the second floor terrazzo in Warch will begin next week.

As always – safety first! Do not enter construction areas! Please be mindful of your surroundings at all times as most construction and projects are really ramping up. Should you have questions or see anything concerning as you’re out and about, please contact Katherine in Facility Services at: Katherine.lehman@lawrence.edu or at ext. 6893

Important Campus Construction & Project Updates

Facilities was able to restore power to Colman and Brokaw Hall at 10:00 PM Tuesday evening. Shout out to that team for staying late and making it happen!

Safety first! Do not enter construction areas! Please be mindful of your surroundings at all times as most construction and projects have begun.

Construction is well under way at Kohler Hall. The lower level is currently being demoed to lay new piping and the window replacement has begun.

Demo of the lower level in Music Drama has also begun for new flooring and HVAC system.

Thank you for you cooperation and patience as we make these many upgrades to our beautiful campus!

Construction update: Power out June 13-14 for Colman and Brokaw

Important announcements as construction and projects are underway!

Reminder: Power will be out for Colman and Brokaw Halls June 13th & 14th as work continues on the Drew Street Bridge

We appreciate your flexibility and cooperation as construction begins full swing next week! Lots of exciting (and not so exciting behind the scenes) changes to come! Please be aware of your surroundings at all times as your safety is priority! There will be construction happening at some point in and around most of the buildings. Watch for updates weekly:

Kohler Hall – The cranes will be moving in Monday to begin work on the new windows

Music Drama – basement demo begins Tuesday for new flooring, along with preparation for a new HVAC system

Res Life renovations kick off on Tuesday

*Please note, the Chapman and Music Drama parking lots will be closed for construction equipment

Should you come across any issues due to the current projects taking place around campus, please contact Katherine with Facility Services: katherine.lehman@lawrence.edu  or extension 6893

Residence hall projects this summer

Here’s a sneak peek at some of the projects that will be taking place in some of the Residence Halls this summer!

Colman Hall

  • New ceiling tiles
  • New carpet in the 2nd, 3rd, & 4th floor hallways

741 E. Boldt

  • Bathrooms renovations on the first floor
  • Kitchen renovation
  • New flooring in the kitchen & living area
  • New furniture in the public space

742 E. Boldt

  • New furniture in the public space

203 N. Union

  • New flooring in living area
  • New furniture in public space

Sage Hall

  • New flooring in the lobby
  • New blinds in student rooms
  • New lighting in student rooms

Brokaw Hall

  • New ceiling tiles on the 3rd & 4th floors
  • New lounge furniture on the 3rd floor

Trever Hall

  • New ceiling tiles in hallways
  • New furniture in the public space
  • Complete new carpet in hallway

Quad 4

  • New public area furniture

Plantz Hall

  • Fresh paint in the lobby
  • New ceiling tiles in the basement lounge

Ormsby Hall

  • New lighting in student rooms
  • Bathroom renovation on the 1st floor

Quad 2

  • Fresh paint
  • New flooring in public space
  • All bathrooms will be renovated

Campus Projects & Construction Updates

The Bee Shed is just about complete and its residents should be moving in any day now!

“The new pollinator education center next to SLUG will serve as an open community space, where anyone can come learn about beekeeping and managing landscapes for pollinators. We will be planting the area with native flowering species and providing habitat for both native bees and honeybees. There will be an observation hive open to the public and lesson plans available for students of all ages,” according to Israel Del Toro, assistant professor of biology.

Also, work is currently under way in the Greenhouse, which will be sporting a new HVAC system when the work is complete.

Campus Projects & Construction Updates

There are many construction projects happening on campus this spring and into the summer. Facilities will keep you up to date on what’s happening with weekly LU Insider posts.

Drew Street Pedestrian Bridge

  • Drew Street to close May 31 through September for the new bridge construction. Please note – power will be shut off June 13 & 14 affecting buildings on the west side of the bridge as demo begins.

Bee Shed

  • The foundation is poured and the frame is up! Israel Del Toro will be utilizing the Bee Shed to introduce a new bee species and boost our local bee population.

Music-Drama Center

  • Music-Drama will be receiving a new HVAC system for better zoned temperature control, along with updated ceiling tiles.

Warch Campus Center

  • 2nd floor flooring will be replaced with terrazzo. Watch for a new elevator later this year!

Ormsby Hall

  • Many behind the scenes upgrades are planned.

Athletic Fields

  • New track is coming soon!

Kohler Hall

  • New windows throughout with Boldt completing renovations.

Brokaw Hall

  • New windows will be installed on the 3rd and 4th floors and mechanical updates.

Quad 2

  • The carpet is being replaced with LVT in the 1st floor public space along with many other improvements. 

Watch for updates weekly!

The Bee Shed frame is up!

Drew Street to close beginning May 31

Construction on the Drew Street foot bridge is scheduled to take place this summer.  As a result, the City of Appleton will be closing Drew Street beginning May 31, 2022, and it will remain closed until September. The Brokaw parking lot will continue to be accessible from Drew Street but the lower level lot near the tennis courts will not.  The footbridge itself will remain open until the day after Commencement, June 13, 2022.

Current and upcoming campus construction projects

  1. Kohler Hall: The Phase I renovation is still underway.  On Friday, September 24th, from 9am-11am, there will be a crane lifting a large fan to the roof of Kohler Hall. Everyone will need to be out of Kohler Hall during this time.
    1. Half of the parking lot will be coned off for the delivery of the crane, which will be arriving around 8:30am and departing by noon. We ask that everyone avoid this area during this crane lift, for safety reasons.
    1. Phase II will encompass the lower level and remainder of the windows over the summer of 2022.
  2. Johnson Controls: Campus-wide lighting upgrade and science building fume hood upgrades in progress.
  3. Briggs Hall Greenhouse: Hot water pipe replacement is in progress.
  4. Brokaw Hall: New ramp expected to be completed in November.
  5. Hiett Hall: Repairs to a broken sewer line. 
  6. Hillside Boardwalk between Hiett Hall and Briggs Hall: Removal of the boardwalk has begun and expected to be removed by late October.

*Projects and dates subject to change